Residential Project
Saudi Arabia
BIM modeling, coordination, and LOD development for a large-scale residential apartment project, supporting construction and as-built documentation.
CHALLENGES
Incomplete IFC inputs at initial stage
Solution: Validated and developed LOD 300 models based on received IFC data
Impact: Established a reliable base model for coordination without design assumptions
Â
Interdisciplinary clashes during coordination
Solution: Performed clash detection using Navisworks and coordinated with project stakeholders
Impact: Reduced site conflicts and improved construction readiness
Â
Requirement for construction-ready and as-built models
Solution: Enhanced models to LOD 400 for construction and LOD 500 for as-built deliverables
Impact: Enabled accurate execution and provided reliable models for O&M use
TECHNICAL HIGHLIGHTS
Technologies: BIM (LOD 300 / 400 / 500)
Â
Tools & Platforms: Revit, AutoCAD, Navisworks, BIM 360
Â
Innovations / Optimizations: Efficient LOD progression aligned with project requirements
Â
Key Metrics: Coordinated multidisciplinary models delivered from LOD 300 to LOD 500
DELIVERABLES
- LOD 400 coordinated construction models
- LOD 500 as-built BIM models
- Clash detection & coordination reports
- Model validation based on IFC inputs
Key Highlights:
25k sqm
Project scale
03
LOD stages executed (300 → 400 → 500)
01
Coordinated BIM workflow implemented
100%
Clash-coordinated and validated models
04
Software used
CONCLUSION
By focusing on accurate model validation and coordination without altering the original design intent we ensured a smooth transition from IFC inputs to construction-ready and as-built BIM deliverables.
Â
Our approach minimized risks, improved coordination, and supported efficient project execution.
Other Articles
Dive deeper into the specifications of our prominent projects and the impact created.

5G UPGRADE – Structural Reinforcement
Integration of new 5G antennas, RRUs, DC/FO routing, pinwheel reinforcement, and mid-panel horizontals on an existing 103.2 m mast tower.

5G UPGRADE – Mount Structure Analysis
To assess the structural capacity of the existing 10.5 ft platform mount on a 148 ft monopole for a proposed T-Mobile 5G upgrade at 132 ft.

5G UPGRADE EJV
eJV Antenna, RRU and ancillary upgrade work on an existing rooftop steel structure. Produced Construction drawing for proposed scope.