5G UPGRADE – Mount Structure Analysis

Indiana, USA

 

To assess the structural capacity of the existing 10.5 ft platform mount on a 148 ft monopole for a proposed T-Mobile 5G upgrade at 132 ft, evaluating the mount under increased loading and defining the strengthening required for compliance with US standards.

5G UPGRADE – Mount Structure Analysis

CHALLENGES

Increased Load from New 5G Equipment
Solution: Conducted detailed mount-level analysis under current & proposed loading conditions
Impact: Established structural adequacy and identified reinforcement actions

High Stress in Bracing Members
Solution: Reviewed member utilization using a RISA-3D model
Impact: Critical members approaching 87.5% utilization were identified, enabling targeted strengtheningl

Constructability Constraints at 132 ft Elevation
Solution: Proposed strengthening components that can be safely installed at height
Impact: Improved installation feasibility

TECHNICAL HIGHLIGHTS

Technologies: 4G/5G

Tools & Platforms: RISA 3D, Excel based wind-load calculator

Environmental Parameters:

  • Design wind speed: 115 mph
  • Exposure category: B
  • Ice thickness: 1.5 in
  • Seismic design category: B

DELIVERABLES

  • Conditional Passing Structural Report
  • Detailed capacity check of mount components
  • Equipment load summary & load combinations
  • Reinforcement recommendations
  • RISA-3D analysis outputs & modeling appendix

Key Highlights:

148 ft

Telecom monopole assessed

132 ft

5G upgrade elevation analysed

115 mph

Wind design verification

87.5%

Critical member utilization identified

4G/5G

Multi-technology upgrade support

RISA-3D

Advanced structural modelling used

CONCLUSION

Our solutions added real value by improving safety, durability, and upgrade readiness. The project was delivered with precise assessments and smart, practical engineering decisions

We’re ready to apply the same expertise and thoughtful problem-solving to your next project.